PALO COLORADO, Monterey County — October 29, 2026. A separate planning matter in the Palo Colorado community concerns a 5,000-gallon water storage tank intended solely for use by the Mid-Coast Fire Brigade during firefighting. The Monterey County Zoning Administrator considered the after-the-fact coastal permit application on February 26, 2026 as PLN240024 / ZA 26-015.
Where is the tank?
The property is adjacent to 37013 Palo Colorado Canyon Road, under the Big Sur Coast Land Use Plan. County staff describe an existing concrete pad and stone-wall enclosure, rather than construction of a new elevated water tower. The site lies within 100 feet of designated environmentally sensitive habitat, which triggered additional coastal review.
What did the applicant seek?
The requested after-the-fact combined development permit would allow the water tank within the existing enclosure and address the nearby habitat area. County staff recommended finding the project categorically exempt under the existing-facilities provision and approving it with two conditions.
What did local advisers say?
The Big Sur Coast Land Use Advisory Committee reviewed the project on February 10. Its members voted 5–0 to support the proposal, suggesting signage that clearly identifies the water supply as for fire suppression only. The reported advisory vote is not itself an issued final permit.
Does the filing confirm operational readiness?
No. Although the application describes a tank already placed at the property, the February staff report does not prove that all conditions, inspections or water-supply requirements have been met. Residents should confirm operational details with the fire organization, not assume the tank is available for public drinking water or domestic use.
Primary source: Monterey County Zoning Administrator ZA 26-015, February 26, 2026. This article distinguishes the established planning record from any unverified later permit outcome.
Support Palo Colorado News
Choose how to support Palo Colorado News:
Credit / Debit Card via StripeChoose your contribution amount on the secure California58 Stripe checkout. One-time support for independent local journalism.
Continue with PayPal Continue with ZelleZelle payments go to Vitaly Ataev Troshin. Please verify the recipient in your bank before sending. Availability depends on your bank.
Optional reader support. When possible, add “Palo Colorado News” to the payment note. Contributions are not advertised as tax-deductible. Support does not influence editorial decisions.More from Palo Colorado News
- Palo Colorado Road ADU Proposal: County Reviewed 1,200-Square-Foot Unit, Septic Work and Three Oak Removals →
- Palo Colorado Road Repair Funding: County Renewed Federal Grant Application After 2024 Round Was Rescinded →
- Palo Colorado: 37-Acre Mill Creek Redwood Preserve Fuel-Reduction Plan Targets Evacuation Access →
- Palo Colorado Road Closure at The Hoist Remains on Monterey County’s Public Road List →
СООБЩЕСТВО
Комментарии
Присоединяйтесь к обсуждению California58. Чтобы комментировать, необходимо войти в аккаунт.
Создайте бесплатный аккаунт California58 или войдите через доступную социальную сеть.